Client:

NFU Mutual

Architect:

Dunnell Robertson Partnership (Keiran Lee)

Duration:

33 Weeks

Date Commenced:

28th June 2010

Value:

£600K

Form of Contract:

JCTIFC 98

Islands Insurance

 

Project Overview

Undertaking a complete refurbishment without impacting on the day-to-day running of this very busy company working closely with the Island Insurance management team, a 33-week schedule of works was put together which included refurbishing the offices, washrooms and creating a new boardroom and staff room.

All three floors were stripped back to their concrete shell before new suspended ceilings, doors and partitions were fitted and the floors and walls were given new finishes. New heating, cooling and ventilation systems were installed and the electrics upgraded. All of the shower and washroom facilities had new sanitary ware fitted and were retiled. The only things in the whole building which weren’t changed were the windows.

Please click on the link below for a project overview pdf:-

IslandsInsurance.pdf


News...

View the news archive


2nd May 2012

R G Falla Complete the Refurbishment of the GRUFC Clubhouse

26th April 2012

The Whitehouse Project Completed On Time and On Budget

5th April 2012

Quarter Marathon Registration Pack

9th December 2011

Working Together at the new St Andrews En Route